Report_Id:   233097   Est NO  0002

Date:11/13/2023

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 233097 Estimate Number 0002 Estimate Type PROGRESS
District Office COVINGTON (06380)  Russell, Shawn P.

Contractor MAGO CONSTRUCTION COMPANY LLC ADDR SN 0 VC Code KY0028714
PO BOX 669
BARDSTOWN , KY , 40004
Pay Period 10/07/2023  TO  10/20/2023
Date Approved 10/29/2023
Primary Proj Number 0609403682401
Project No. CB06 094 0368 000-005
Primary County OWEN
Name of Road CEDAR CREEK ROAD (KY 368)
Description FROM FRANKLIN CO LINE, EXTENDING NORTH TO TRUESVILLE RD (CR 1256).
     
     
Date Let 08/24/2023 Formal Acceptance
Date Awarded 09/01/2023 Date Work Began 10/05/2023
Date Contract Executed 09/08/2023 Open To Traffic
Date NTP Issued 09/08/2023 Actual Completion Date

Current Contract Amount

$417,452.00

Total to Date

Prev to Date

This Estimate

Original Amount

$417,452.00

Total Earnings

$359,234.81

$61,146.49

$298,088.32

Percent Complete

86.05

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$58,217.19

Gross Earnings

$359,234.81

$61,146.49

$298,088.32

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$359,234.81

$61,146.49

$298,088.32

Contract Id 233097

Change Order Summary

County OWEN
Estimate Nbr 0002 Project Number CB06 094 0368 000-005
Contractor MAGO CONSTRUCTION COMPANY LLC Period 10/07/2023  TO  10/20/2023
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 233097

COMMONWEALTH OF KENTUCKY

County OWEN
Contract Type ASRS   ASPHALT RESURFACING

TRANSPORTATION CABINET

Primary Project Number 0609403682401
Estimate Nbr 0002 Period 10/07/2023  TO  10/20/2023
Contractor MAGO CONSTRUCTION COMPANY LLC
 
Project 0609403682401 Fed/State Project Number CB06 094 0368 000-005 Category
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
Project 0609403682401 Fed/State Project Number CB06 094 0368 000-005 Category 0001 ROADWAY
0005 LEVELING & WEDGING PG64-22 00190 TON 860.00 860.000 674.350 170.570 844.920 91.00 61,365.85 76,887.72
0010 CL2 ASPH SURF 0.38D PG64-22 00301 TON 3,155.00 3,155.000 2,601.200 462.310 3,063.510 91.00 236,709.20 278,779.41
0015 ASPHALT MATERIAL FOR TACK 00356 TON 36.00 36.000 13.270 0.490 13.760 1.00 13.27 13.76
0020 TEMPORARY SIGNS 02562 SQFT 310.00 310.000 136.000 136.000 0.01 1.36
0025 MAINTAIN & CONTROL TRAFFIC (KY 368) 02650 LS 1.00 1.000 0.000 0.000 5,200.00 0.00
0030 MOBILIZATION FOR MILL & TEXT (KY 368) 02676 LS 1.00 1.000 1.000 1.000 3,200.00 3,200.00
0035 ASPHALT PAVE MILLING & TEXTURING 02677 TON 60.00 60.000 29.380 29.380 12.00 352.56
0040 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 47,300.00 47,300.000 0.000 0.000 0.01 0.00
0045 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 47,300.00 47,300.000 0.000 0.000 0.31 0.00
0050 FUEL ADJUSTMENT 10020NS DOLL 6,250.00 6,250.000 0.000 0.000 1.00 0.00
0055 ASPHALT ADJUSTMENT 10030NS DOLL 15,697.00 15,697.000 0.000 0.000 1.00 0.00
Project 0609403682401 Fed/State Project Number CB06 094 0368 000-005 Category 0002 DEMOBILZIATION
0060 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 5,844.90 0.00

SUBTOT

$298,088.32

$359,234.81

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00